Prospecthill Court, Pioneering Tower Block Retrofit

Client: River Clyde Homes
Services: Energy Modelling

Overview

QODA provided energy modelling for the retrofit of Prospecthill Court, a 16-storey residential tower block in Greenock. Commissioned by River Clyde Homes, the project demonstrates how existing social housing can achieve substantial improvements in energy performance while retaining its original structure.

The retrofit was completed in September 2024 and achieved the AECB CarbonLite Retrofit Standard in August 2026. Analysis of heat meter data across 90 flats showed a 47% reduction in combined space heating and hot-water consumption.

Project vision

The project aimed to reduce heat loss, improve residents’ comfort and help tackle fuel poverty by upgrading the existing building. Retaining and improving the tower also avoided the need for demolition and replacement, preserving the original structure and reducing the demand for new construction materials.

The approach combined improvements to the building fabric with energy modelling and monitoring to assess performance in everyday use.

Key features

Improved building fabric

Insulated external rainscreen cladding, triple-glazed windows, airtightness measures and mechanical ventilation improve thermal performance and support a healthier indoor environment.

Measured energy savings

Heat meter data from 90 flats showed a 47% reduction in combined heating and hot-water consumption, comparing October 2023 to September 2024 with October 2024 to September 2025.

Fabric, Comfort & Performance

While fabric upgrades were necessarily limited by heritage constraints, targeted improvements were introduced to enhance thermal performance and operational efficiency. These were complemented by efficient ventilation and environmental control strategies tailored to high-humidity and high-occupancy leisure environments, ensuring robust performance, occupant comfort, and resilience in use.

Low space heating demand

Certification evidence established a space heating demand of 34 kWh/m²/year, below the applicable AECB target of 50 kWh/m²/year.

Pioneering certification

The project received the UK’s first special-category AECB certificate under its Tall Buildings Retrofit Protocol, establishing a precedent for assessing large, occupied residential buildings.

QODA’s role

QODA provided energy modelling using the Passive House Planning Package (PHPP) to assess the building’s performance before and after retrofit. The modelling predicted a 47% reduction in combined space heating and hot-water demand, closely matching the reduction subsequently recorded through heat meters.

Certification was undertaken by Steven Coulsting, formerly of QODA. With reliable whole-building airtightness testing difficult to carry out in an occupied tower, testing of selected flats was combined with energy consumption evidence to support assessment under the AECB’s Tall Buildings Retrofit Protocol.

The wider project team included BDP as architect, Kier Construction as contractor and Currie & Brown providing construction and cost management. River Clyde Homes’ former Technical Services Lead, David Eadie, supported the project and compiled the consumption data used to evaluate its performance.

Impact

Prospecthill Court provides measured evidence of the benefits of retaining and upgrading existing social housing. Its reduction in heat consumption supports lower heating costs, while the renewed building envelope provides long-term weather protection.

The project also establishes a route for demonstrating retrofit performance in occupied tower blocks, where conventional testing presents practical challenges.

As Tim Martel, AECB Standards and Certification Programme Manager, described it:

“This is a truly pioneering retrofit project.”

Related projects

Seymour Leisure Centre – Heritage Redevelopment into a Modern Wellbeing Leisure Centre

Seymour Leisure Centre – Heritage Redevelopment into a Modern Wellbeing Leisure Centre

Read More
Guernsey Football Association, New Stadium & Community Hub

Guernsey Football Association, New Stadium & Community Hub

Read More